Friday, 8 February 2013

The project is now complete after a seamless handover to Kirklees council on Thursday 7th February. The project was completed to a high quality standard both internally and externally with complimentary remarks from the client and clients representative. Another excellent project delivered from the Wates Kirklees Team. A big thankyou to all involved.
 

 

Tuesday, 5 February 2013

Internally, we have nearly completed the snagging list produced by Kirklees Council.
 
Externally, we have completed the bin stores and perimeter fencing. The Yorkshire Water inspector and Building Control have inspected the drainage runs.
 
The turf is due to be layed next Monday, followed by flags and block paving jet washed ready for the client inspection!