Tuesday, 18 December 2012

The Wates team and our sub-contractors would like to thank you for your continued patience whilst we have been on site at Hare Park Grange.

Our site will close for the Christmas period on Friday 21 December, and will re-open in the new year on Wednesday 2 January.

Can we also take this opportunity to wish you a merry Christmas and a happy new year!


Monday, 17 December 2012

Externally we are fighting the winter elements continuing with flagging and forming the path ways ready for tarmacing. Internally the flats are looking cosy already. We are continuing with the 3rd fix items, testing, commissioning and snagging.
 
 

Friday, 7 December 2012

Externally despite the noticeable change in the weather we are continuing with the flagging and block paving to the parking bays. Internally Block 1 is very much as last week all doors and ironmongery are on, decorating is on going with the 3rd fix items shelves, bathroom curtains etc. Block 2 is ready for final decoration and then hanging the doors.
 
 

Monday, 3 December 2012

Externally we are continuing kerbing and flagging to the front of Block 1. Internally in block 1 we are continuing decorating, 3rd fix joinery, hanging doors and fixing iron mongery. In block 2 we have completed the tiling and are continuing the 2nd fix mechanical and electrical, allowing the decorators to complete their work.