Friday, 21 September 2012

Internally, we are carrying on 1st fix mechanical followed by the 1st fix electrical.  Once a flat has been handed over, we proceed to close up the ceiling and walls. 
 
We are are fixing plywood to the kitchen and bathroom walls for extra strength for wall cabinets etc.  
 
 

 

Thursday, 20 September 2012

With the 1st floor acoustic floors complete, we commenced with the building of the internal walls allowing us to commence with the 1st fix mechanical later on in the week. This will be followed next week with the 1st fix electrical. The plots are really taking shape now.
 

Last week saw us progress the internals.  Once the acoustic floors on the 1st floor were installed, we set out the internal walls and boarded one side which released work for the mechanical installation, which commenced back end of the week. The perimeter walls and ceiling on the ground floor are continuing and this week we will be setting out the internal walls on the ground floor ready for mechanical and electrical installation.


Tuesday, 11 September 2012

Last week saw us almost complete the brickwork up to the eaves on the front elevation which will be completed early next week.
 
Internally we are progressing with the acoustic floors on the 1st floor and boarding the ceilings and perimeter walls on the ground floor. Once they have been taped and jointed this will allow us to set out the internal walls.