Externally we are continuing with installing the water and electric services to the plots. Also at the top of site we are block paving the parking bays, forming the road and path in front of the garages. Internally we nearly have a full compliment of trades, continuing on are plasterers in plots 17 & 18 behind following on are plumbers 1st fixing the kitchens,bathrooms and radiators then Joiners fitting kitchens, skirting and architraves. This weeks new addition tillers tiling the bathroom and kitchen.
Friday, 26 October 2012
Friday, 19 October 2012
Thursday, 18 October 2012
Externally the ground workers completed the parking bays ready for the relocation of the cabins on Monday. We will then concentrate on the installation of the services, gas, water, electric and BT.
Internally we are progressing with closing up the walls and plastering. Some plots the plaster has dried sufficiently for us to mist coat followed by the fitting of the casing, architraves and skirting. The 2nd fix plumbing has commenced with the fitting of the boilers and associated pipework to the kitchens, this will enable us to install the kitchen units next week.
Monday, 8 October 2012
We have managed to complete the render and mastic to the 1st floor windows which has enabled us to commence with the stripping of the scaffold starting with block 2 . The groundworkers can now return to lay the services and complete the externals. We are concentrating on the parking bays so we can relocate our site cabins.
Internally we are progressing nicely with the 1st fix mechanical and electrical, following on with the plastering. We have plots now which are dried out and ready for the mist coat of paint. This then allows us to fix the boilers and radiators. Next week we can the start 2nd fix joinery, door casings, skirting and architrave.
Monday, 1 October 2012
This week we have completed the 1st fix mechanical and electrical in some flats enabling us to close the walls and commence plasterering. This is a rolling process through the plots.
Externally we have managed to complete a couple of rendered panels inbetween the heavy downpours. We need to complete the render before stripping the scaffolding.