Monday, 26 November 2012

Externally we have commenced block paving the parking bays, flagged around the back of block 2 and commenced laying the kerbs to the haul road.
 
Internally we are continuing 2nd fix electrical and testing 3rd fix mechanical, fixing taps and showers etc. The decorations are complete in some plots allowing us to commence with the 3rd fix joinery items including doors,shelving and bath panels etc.
 

 

Monday, 19 November 2012

Externally we are forming the parking bays in front of Plot 1,  laying the edgings and aco drains and the electric meters are now being fitted.
 
Internally we are progressing well the kitchens are installed, the bathrooms are 2nd fixed complete, the vinyl flooring in the kitchens and bathrooms is almost complete and the decorators have started finishing the walls and glossing the wood work.
 

 

Monday, 12 November 2012

Externally we have base coated the road and path in front of the garages. Also commenced laying the paving slabs to the rear of block 1, working our way around to block 2. Internally we have installed the kitchens in block 1 continuing with the tiling and 2nd fix electrics which include lights and sockets. Also fitting the toilets and pipe boxings giving the decorators a clear run on Monday .
 



 

Friday, 2 November 2012

The installation of the kitchens and bathrooms is progressing well, with decoration due to follow in the next couple of weeks.

The plaster works is all-but completed and the flats are starting to take shape nicely.
Some of the plots now have the vinyl fitted to the bathrooms and kitchens, although they are protected and covered so can’t always be seen.

Externally the ground-workers have started to shape up the front and rear of the properties and now gives a better idea of the profile of the area.