Monday, 16 April 2012

This week we have steadily continued with the drainage runs, making sure to locate all existing services by a series of very meticulous hand digs.  We have had Yorkshire water out to inspect our work, who I am happy to say are pleased with our processes.
 
We have surveyed the levels of the foundations to block 1, plots 1-9, and completed the concreting to the footings.  We also started to pump out the rain water which had filled up the area where the attenuation tank will be laid early next week......to the dismay of a few of the locals..... see picture !