Tuesday, 8 May 2012

Thanks to the better weather we were able to progress with the substructure masonry as planned on block 1.  Also by the middle of this week, the plot drainage runs on plots 1-14 will be complete.  We had a groundworking team carrying on with the rainwater attenuation system, and have been working closely with the Yorkshire Water inspector with regular site inspections.

This week we will continue with sub-structure blockwork and the main drainage run.