Thursday, 20 September 2012

Last week saw us progress the internals.  Once the acoustic floors on the 1st floor were installed, we set out the internal walls and boarded one side which released work for the mechanical installation, which commenced back end of the week. The perimeter walls and ceiling on the ground floor are continuing and this week we will be setting out the internal walls on the ground floor ready for mechanical and electrical installation.