Monday, 12 November 2012

Externally we have base coated the road and path in front of the garages. Also commenced laying the paving slabs to the rear of block 1, working our way around to block 2. Internally we have installed the kitchens in block 1 continuing with the tiling and 2nd fix electrics which include lights and sockets. Also fitting the toilets and pipe boxings giving the decorators a clear run on Monday .