Friday, 7 December 2012

Externally despite the noticeable change in the weather we are continuing with the flagging and block paving to the parking bays. Internally Block 1 is very much as last week all doors and ironmongery are on, decorating is on going with the 3rd fix items shelves, bathroom curtains etc. Block 2 is ready for final decoration and then hanging the doors.