Monday, 18 June 2012

The weather was kind to us last week, enabling us to pour the concrete slabs on Wednesday and Thursday.  The rain held off until we floated the floors and the concrete had set. We have commenced with the timber frame wall plates which will be ongoing this week. 
 
We are shaping up the entrance haul road ready to receive the base course of tarmac, this will transform the site.
 
Today we will stone up the perimeter of block 1 (the larger block) to commence the scaffolding to the perimeter on Tuesday, leading up to the installation of the timber frame next week.