The week ending 3 June, we commenced with the gas proof membrane and perimeter / internal wall plinth blocks for the timber frame on block 1. We also completed the substructure blockwork to block 2, ready for the installation of the block and beam.
Last week saw the block and beam installation, on schedule, with the crane positioned on the road lay-by again.
The weather turned again, which saw us fighting the elements proceeding with the gas proof membrane and the plinth blockwork to block 1.