Externally the ground workers completed the parking bays ready for the relocation of the cabins on Monday. We will then concentrate on the installation of the services, gas, water, electric and BT.
Internally we are progressing with closing up the walls and plastering. Some plots the plaster has dried sufficiently for us to mist coat followed by the fitting of the casing, architraves and skirting. The 2nd fix plumbing has commenced with the fitting of the boilers and associated pipework to the kitchens, this will enable us to install the kitchen units next week.