We have managed to complete the render and mastic to the 1st floor windows which has enabled us to commence with the stripping of the scaffold starting with block 2 . The groundworkers can now return to lay the services and complete the externals. We are concentrating on the parking bays so we can relocate our site cabins.
Internally we are progressing nicely with the 1st fix mechanical and electrical, following on with the plastering. We have plots now which are dried out and ready for the mist coat of paint. This then allows us to fix the boilers and radiators. Next week we can the start 2nd fix joinery, door casings, skirting and architrave.