Friday, 26 October 2012

Externally we are continuing with installing the water and electric services to the plots. Also at the top of site we are block paving the parking bays, forming the road and path in front of the garages. Internally we nearly have a full compliment of trades, continuing on are plasterers in plots 17 & 18 behind following on are plumbers 1st fixing the kitchens,bathrooms and radiators then Joiners fitting kitchens, skirting and architraves. This weeks new addition tillers tiling the bathroom and kitchen.