Last week saw another busy week, with 3 days of crane lifts.  Monday saw us erecting wall panels and lifting the trusses off, then back on the built wall panels to plots 2, 4, 6 and 8.  The process was repeated on Tuesday to plots 10, 12 and 14.  This saw block 1 trusses complete.
 
On Thursday block 2 trusses were lifted into place.  Scaffolders then erected the edge protection to the gable end, at the same time we netted the roof joists ready for the roof covering on block 1 on Monday.  With the added pressure of the crane costs it all went like clockwork.  A good weeks' effort by all !