This week saw us concentrating on getting the block 1 water tight.  First installing the fire socks and eaves ventilation, continuing with the soffits and fascias then felt and battening the roof, enabling us to load the roof with roof tiles.  We also commenced with the installation of the windows. With all this achieved we can put our feet up this weekend and enjoy the opening ceremony of the 2012 Olympic games!