This week was a busy and productive week, with 3 days of crane lifts, Mon and Tue installing the 1st floor cassettes, and Friday saw the roof trusses lifted into position so they can be set out and erected on the 1st floor.
Also in-between the crane being on site, the scaffold was erected to the 3rd lift.